Segment 7
|
Where:
South of I-85 near Archdale to US 220, near Sophia, Randolph
County
Length: 13 Miles Needed: Finish Constructing New Freeway Current Highway signed: |
I-74 will continue on a new freeway from
south of I-85 near current Exit 113 in Archdale to US 220 (I-73) near
Sophia, north of Asheboro, connecting to US 220 south of the current
US 311 interchange along a path approximated by the red dashed
line in the map above. When this specific route was chosen in 1997
it disappointed many citizens and government officials in the area
since the route cuts a 1000 foot wide path directly through the
city of Sophia before meeting US 220. Despite many objections, NCDOT
chose this route, designated Corridor C, rather than the Corridor
AA route prefered by the public at June 1997 hearings, because it
cost $7 million less, avoided a complicated interchange with US 220 (I-73),
and would send the least amount of pollution to the future Randleman
Reservoir, preventing potential environmental problems. (1, 2) The
project is listed in the Draft 2009-2015 NCDOT STIP as Number R-2606.
(3) Right-of-Way acquisition started on the western part of the route
in 2003, with a total cost projected at $17.5 million. Construction
on the first section, $28.5 million of
the total construction cost estimated at $177 million, started on May 29,
2007 (see below). (4) This section will feature an interchange at
Cedar Square Road (listed in contract documents as Exit 79) which will
be the temporary end of I-74 while the other segments are still under construction.
US 311 will be temporarily routed along Cedar Square road back to its
current alignment. The US 311 route from there westward (northward) will
be redesignated US 311 Business. (5) The next two segments totalling
7.9 miles will be built as design-build projects to be let in July 2008
and construction to start a month later. There will be an exit for current
US 311 in Sophia and the interchange with US 220 along this segment. (6)
This
segment has been dubbed the "Missing Link" by the I-74 Piedmont
Corridor Group (PCG), an organization of business people, transportation
officials, and others lobbying to complete I-74. They created
the term in 2003 to call attention to what they saw as NCDOT's too
drawn-out segmented plan to complete this portion of the highway,
long after many other sections of I-74 were then scheduled to be built.
The PGC hoped to put enough pressure on NCDOT to move up its construction
timetable for the entire section to match work starting on Segment 6 to the west. Starting both projects
at once, supporters said, would be more efficient. (7) This effort
seems to have eventually paid off. While start of construction
was delayed from October 2006 to May 2007, work on the first part,
5.3 miles from south of I-85 near Archdale to north of Spencer Road
(SR 1929) in Glenola,(8) will began at the same time as work was started
on the remaining section of Segment 6. (9)
Here's some photos of construction so far for the I-85/I-74 and NC
62 interchange:
Road grading is proceeding just south of I-85 and east of NC 62. Taken from road which will be split by the new interstate (2/23/08)
A completed bridge pier can be seen in the distance, perhaps part of a flyover ramp from I-74 West to I-85 South (2/23/08)
Looking eastbound at the clearing being done for the interchange, September 2007.
Here's the
view approaching the construction area on I-85 North, lanes are restricted
in the area from 3 to 2,
September 2007.
Here's a view of more land clearing a couple miles east of I-85.
Also,
whereas earlier plans called for the proposed letting for the next
part of the highway, 5.6 miles from Spencer Road to the current US
311 west of Sophia, not to occur until after 2012 and the final part,
2.3 miles from current US 311 to US 220 through Sophia not to begin
a couple years after that (10), the new STIP indicates
most of the funds will be borrowed under the Garvee Bond Program to
expedite work on the next two sections starting in the latter half of
2008. These borrowed funds ($112 million) would then be paid back out
of the highway fund accounts through 2019. (3) The first section then
should be completed by 2011 and the entire segment may be finished by
2012.
A summary
of construction through May 2008 (11):
Baker Rd. - Much
clearing has done at the location. They may have to alter this intersection
as it falls within the right-of-way and may want to keep the road open if
other roads are closed in the area.
Jackson Lake Rd. - Piers for the bridge over this road have been put
in. Covered detour signs have been put up meaning the road may be closed to
build the bridge where I-74 will cross.
Kersey Valley Rd. - Work on excavating the road for the bridge hasn't
made much progress since last fall. The road itself is closed and
Dresden Road is used as a detour. There may be two Dresden Roads constructed
as service roads for the homes along the "old" Dresden Rd.
The 311 - I-85 interchange. Footings for bridge structures are under
construction, one being already complete (see photo above.
Tuttle Rd. - A large concrete footing has been poured with more to take
place as part of a major reconstruction of this road across I-74/US 311.
Fill for the roadway has been placed up to the western edge of where the
bridge will be placed.
NC 62's ramp to I-85 has
been closed and fill is being placed on both sides of I-85 in anticipation
of detours needed to construct the bridge over the new I-74 freeway.
Comment: After this section of freeway is built to replace US
311, decommission this intrastate US route which doesn't meet current
AASHTO U.S. Route guidelines (at least 200 miles long, in more than 1
state). The section north of I-40 (not along I-74's route) could
be NC 311.
Here's a map from the Greensboro
News & Record showing the new sections of I-74 under construction:
If anyone is willing to share other photos from the roads in the vicinity of this segment, feel free to E-mail me.
Sources: NC Transportation Map 2001.
(1) Hall, Tony. 1997. "I-74 Coming to
a Town Where It's Not Welcome." News & Record (Greensboro,
NC). Sept. 27: B1.
(2) Muschick, Paul. 1999. "Route for 311 Bypass to be
Unveiled in Randleman." News & Record (Greensboro, NC).
August 9.
(3) NCDOT. Nov. 2007. State Transportation
Improvement Program, Draft, 2009-2015, Division 8, p. 8-24.
(4) NCDOT. 2007. Construction Progress Report, Contract C201715,
Downloaded May 29, 2007.
(5) NCDOT. 2006. Contract Documents,
NCDOT Signing Section, Contract C201296, Project R-0609-A. Downloaded
from link at: http://dotw-xfer01.dot. state.nc.us/dsplan/2007%20Highway%20Lettings/4-17-2007/ on 2/23/07.
(6) NCDOT. 2008. "R-2606B Timeline for Design-Build Team Selection
Process." NCDOT Construction Unit, Design-Build web page, accessed 2/14/08.
(7) Kimbrough, Pat. 2003.
"Randolph Leaders Lobby State for I-74." High Point (NC) Enterprise.
Dec. 1.
(8) NCDOT. 2007. Program Development Branch. "12 Month
Tentative Letting List for April 17, 2007" (Typically construction
projects are approved and/or start a month after the project is
let, this project is to start the last week in May).
(9) Dominello, Amy. 2005. "U.S. 311 Bypass Work Delayed."
News & Record (Greensboro, NC). May 2, downloaded
from http://blog.news-record.com/staff/fastforward/archives/2005/05/from_sundays_pa.html,
Oct. 1.
(10) NCDOT. Sept. 2004. R-2606 Project Breakdown
Map.
(11) Information from e-mails from Bill Travers 3/6/08, 5/23/08.
US
311 shield courtesy of David R. Kendrick's Shield's
Up!
|
|
|