Segment 6
|
Where:
US 311 High Point East Belt Bypass, North Main Street,
High Point, to South of I-85, Guilford
County
Length: 11 Miles Needed: Construct New Highway (Two-Thirds Complete) Completion Date for Final Part: May 2011 (Perhaps
Earlier) Completed Highway signed as:
|
I-74 will continue
along US 311 on what is now referred to as the
"East Belt" bypass of High Point. The project to build
this segment (Number R-609) was broken up into three
parts. (1) The first two parts are complete. Part one, from where US
311 originally left the freeway at Main Street (now Exit 65, Bus.
311) to NC 68, Eastchester Drive (photo below), almost 2 miles in length,
was completed in 1997. The second part, 4.5 miles
from NC 68 to US 29/70 (Business Loop I-85), was opened on
November 20, 2004 after a delay of nearly a year (2). Once
this section was completed US 311 was re-routed along the completed
bypass to Business 85. The exits on both parts were numbered
originally on US 311 mileposts, but were renumbered in 2008 to
I-74 based mileposts (for an I-74 exit list, go HERE), to match those
put up at the same time on Segment 5. The newly opened section,
like its older predecessor, appears to be up to interstate
standards, however NCDOT has indicated that some parts
are or will not be built to these standards initially. (3) Though
some news reports have indicated NCDOT is not planning to sign
the highway as I-74 until the freeway is completed to US 220 (I-73),
(2) documents posted by NCDOT for the last section
contract letting in late 2006 included detailed plans showing the
placement of I-74 signage along the entire stretch of highway at
the conclusion of the project. (4) Photos from the two complete sections
are below. The Right-of Way acquisition
phase for the last part (6.7 miles from Business 85 across I-85
to Tuttle Road, SR 1920 near Archdale) was delayed a year,
to 2003, due to environmental concerns about the road's path
being near the new Randleman Reservoir, a future drinking
water source for Greensboro. (5,6) For the 2007 contract letting this segment
was split further into smaller pieces with part of the contract (the piece
a mile east of I-85 to Tuttle Road) assigned to the contract for the next
segment (R-2606). The winning contractor, Blythe Construction put in a
combined bid ($104 million) for both projects. Construction started on
May 31, 2007 three years after first scheduled for 2004. (7) There was a
ceremonial groundbreaking for the project on July 16, 2007, for the official
press release go HERE.
(8) According to the NCDOT press release indicating the contract
was approved, the tentative completion date is May 2011 (the
press release indicated the mileage for the entire project from
Business 85 to Spencer Road was 6.4 miles, this was due to an
error in the letting documents that indicated the distance was in
kilometers, the NCDOT public affairs staff putting the release together
dutifully translated the given distance of 10.2 'km' back
to miles). (9) As indicated in the 2009-2015
STIP, total costs for building this entire segment are now estimated
at $242.8 million. (1) The I-85 interchange will be near
the existing NC 62 exit, traffic will exit for both NC 62 (to be Exit 113A)
and I-74/US 311 (Exits 113B and C) using the same exit ramp on I-85 south.
(4) In May 2008 in anticipation of construction of the I-85 interchange
they closed the ramp from NC 62 to I-85 South and have started putting fill
in the area surrounding the interchange. I-74 will pass under I-85 so it
will was necessary to build the C/D ramps for the future I-74 interchange
first and then, in October 2008, place I-85 in both directions temporarily
on these ramps so that bridges can be constructed for I-85 to go over I-74
without affecting traffic. (10) The new bridges appeared close to completion
in September 2009. Because the construction progress is ahead of schedule,
it is possible the route could be open, at least to I-85, before the anticipated
May 2011 completion date.
Photos taken along the completed parts of the US 311 Bypass parts in 2004 (Segments 1 and 2):
Photo shows progress on constructing the ramp from Kivett Drive in High Point to Future I-74 East (US 311 South) in October 2003.
The US 311 Bypass (I-74) interchange and bridge over Kivett Drive in High Point almost a year later, the day after the bypass opened. (November 21, 2004).
Here' the unopened ramp from I-74 West/ US 311 North which leads to the current construction area (September 2007).
A summary of current construction (now 78% complete) on the remaining section through mid-September 2009 going west to east, with photos (from most recent to oldest) below (11):
Baker Rd.
Bridge - The new road around the future bridge was completed in
early June and is now open to traffic. Therefore they are just temporarily
re-routing traffic to the north through the future highway right-of-way
until the new bridge is completed. Work started on the bridge in July and
as of the middle of November excavation of the roadbed had been completed
along the support work needed for the bridge, all the steel supports having
being added by early November:
The crane placing the support beams can be seen in the distance.
(10/12/09)
The crane can be seen lowering
the first beam into place in early October. (10/12/09)
A closer look at the equipment
that loads the support sections in place, three sections make up one span
for the bridge. (10/12/09).
Looking east in September when the crane had just been brought
in to lift the concrete forms into place and then the bridge girders in October.
(9/18/09)
The photo from April shows the beginning of construction on Baker Road with work on building a temporary road to the north of the existing one. This was done so that traffic could still use the road on a new alignment while the bridge was being built. (4/5/09).
Jackson Lake Road Bridge - The bridge was completed and opened to traffic at the end of November 2008.
Here's a view of the
bridge itself heading south toward NC 610. The changes since have
mainly consisted of consolidating the excavated material besides the road
bed, so it can be removed, this was still going on in early August 2009.
(11/23/08)
The view east from the bridge in November 2008, notice progress on excavation, but where the roadway will be is not as obvious as it is a year later. (11/23/08)
Kersey Valley
Rd. - This bridge was completed in October 2008. A road off Kersey
Valley called Dresden Road (where the truck is seen turning on the right)
was used as a detour route and now is a service road now that the next
street that intersected it has been blocked and highway excavation and
cut off (see photo below).
Approaching the newly opened bridge from the southwest (10/31/08)
The view of
the bridge from Dresden Road in September 2009, notice less piles of dirt
and more construction vehicles and equipment than in the photos below. This
is because much of the dirt has been pushed off and up from the road bed.
(9/18/09)
The excavated materials
have been piled on the side of the eastbound lanes during the summer of 2009.
What's left in the roadbed median are construction materials that were
there in the July as seen in the photo below. (9/18/09)
Here's the view of the bridge in June showing how much of the excavated material at that time had been removed by September. Much has been piled off to the side of the roadway by August so that it can be moved to from the slope seen above. (6/14/09)
Here's the view of the bridge in October 2008 showing the further excavating that was needed. (10/31/08) from the then blocked off roadway intersecting Dresden Road. The material in front of the bridge largely remained until at least the end of April 2009.
Here's the view from late October showing what was excavated at that time, including the roadway later removed (see above) (which already had been blocked by barriers) in the center. (10/31/08)
View showing progress of clearing and grading the future I-74 roadway between I-85 and Kersey Valley Road in November 2009. Compare with the view below from last spring. (11/8/09)
The appearance of the future I-74 roadway between I-85 and Kersey Valley Road from last April. (4/5/09)
Here's the view in October, showing progress with grading the roadway since then. (10/31/08)
The I-85 / US 311 - I-74
interchange.
Footings for bridge structures were completed over the summer of 2008
and C/D lanes constructed for the future interchange, traffic was switched
on I-85 in both directions onto the C/D lanes once completed in October 2008
so the I-85 road could be excavated for the I-74 freeway. Progress has
been made on on both the I-85 bridges amd building the flyover ramp that
will carry I-74 East traffic to I-85 north since. Compare the photo below
to those taken in June and early April 2009 and in November 2008.
Work still remains on building
the walls for the I-85 roadway over I-74, there also appears to be little
asphalt on the southern roadbed after the flyover. (11/8/09)
This is the bridge
over I-85 going north, unfortunately, they put back up the fence surrounding
the highway, so I could not duplicate the shots from below, but had
to take two. (6/14/09)
This is a complete photo of the I-85 South future interchange with I-74. The future I-74 and NC 62 exit C/D lanes are now serving as the I-85 mainline temporarily as the old road is excavated (the start of which is going on behind the bridge) to put I-74/US 311 under existing I-85. Above is the progress of construction as of April.
The same view from late October 2008. (10/31/08).
The view of the now cut-off Dresden Road in April 2009 with the future I-85/I-74 interchange in the distance. (5/5/09)
A similar view from April shows progress on the I-85 bridges at that time and the beginnings of the construction of the ramp from I-74 east to I-85 and its continuance on the flyover ramp in the distance. (4/5/09)
Here is a similar photo from last fall. The bridge above I-85 is a part of the I-74 east interchange fly-over ramp, you can see that the ramp to I-85 south is already paved. (11/23/08)
You can also
see in this photo that the closed southbound lanes of I-85 has been excavated.
(11/23/08)
As mentioned above this ramp system southbound will also serve as access to NC 62. These ramps were closed for much of October as they were re-aligned to meet the new C/D ramps. The exit number will be changed to 113A. (10/31/08)
Exit 65 US 311 Business* High Point [25]
Exit 66 Johnston St [24]
Exit 67 NC 68 to I-40 Eastchester
Drive [23]
Exit 69 Greensboro Rd [21]
Exit 70 Kivett Drive [20]
Exit 71A Green Street (WB only) [19B]
Exit 71 (71B WB) Bus. Loop 85/ US
27/ US 70 Thomasville Greensboro [19(A)]
This will be applied
when the freeway is completed in 2011:
Exit 75A/B I-85 Greensboro Charlotte
Here are some photos of
the US 311 signs with the new numbers:
Going Eastbound
(north of US 311), this is the first overhead with two exit signs showing
the new numbers. (12/14/08)
Continuing East you have signs for the Greensboro Road and NC 68 exits. (12/14/08)
The route goes to two lanes westbound after the Exit 67 exit. (12/14/08)
As you can see, they're not ready to put up I-74 signs on the BGSs or along the highway at this time. (12/14/08)
If anyone has other photos taken in the vicinity of this segment they would like to share, feel free to E-mail me.
Sources: Map-ADC North Carolina Road Atlas 1999, p. 124;
(1) NCDOT.
June 2008. State Transportation Improvement Program, 2009-2015,
Division 7, p.7-18.
(2) Dominello, Amy.
2005. "U.S. 311 Bypass Work Delayed."
News & Record (Greensboro, NC). May 2, downloaded
from http://blog.news-record.com/staff/fastforward/archives/2005/05/from_sundays_pa.html,
Oct. 1.
(3) NCDOT. 2006. "I-73/74 Fact Sheet,
Interstate System 50th Anniversary." Downloaded from lhttp://www.ncdot.org/
public/50thanniv/ncinterstates/download/factsI73-74.pdf
(4) NCDOT. 2006. Contract Documents,
NCDOT Signing Section, Contract C201275, Project R-0609-IA.
Downloaded from link at: http://dotw-xfer01.dot. state.nc.us/dsplan/2007%20Highway%20Lettings/4-17-2007/
on 2/17/07.
(5) Schultz, Sue and Paul Muschick.
2002. "State Puts Conditions on Bypass; Officials
Are Struggling to Build a Highway Near the Randleman Reservoir."
News- Record (Greensboro,
NC), High Point/Randolph/Rockingham Edition. Feb. 14:
B1.
(6) Johnson, Paul
B. 2004. "Bypass Opening Stalls." High Point Enterprise.
Sept. 22.
(7) NCDOT. 2009. Construction
Progress Report, Contract C201715, last downloaded October
5, 2009.
(8) Journal Staff. 2007. "REGIONAL BRIEFS-Ground
to be Broken for Next Leg of Corridor." Winston-Salem
Journal. July 10.
(9) NCDOT. 2007. "Transportation Board Awards
$104.2 Million Contract to Construct 6.4 Miles of U.S. 311
in Guilford and Randolph Counties." Press Release. May 4. Downloaded
from https://apps.dot.state.nc.us/pio/releases/details.aspx?r=1135,
May 4, 2007.
(10) Information via e-mail
from Bill Travers 5/23/08.
(11) Information from e-mails from
Bill Travers 8/11/08, 10/20/08, 6/13/09, 8/2/09.
I-74 and US 311 shields courtesy of David R. Kendrick's Shield's Up!
|
|
|