Segment 6
|
Where:
US 311 High Point East Belt Bypass,
North Main Street, High Point, to South of I-85,Guilford
County
Length: 11 Miles Needed: Construct New Highway (Two-Thirds Complete) Completion Date for Final Part: Nov. 2010 (Perhaps Earlier) Completed Highway signed as:
|
I-74 will continue
along US 311 on what is now referred
to as the "East Belt" bypass of High Point. The
project to build this segment (Number R-609) was broken up into three
parts. (1) The first two parts are complete. Part one,
from where US 311 originally left the freeway at Main
Street (now Exit 65, former Bus. 311) to NC 68, Eastchester Drive
(photo below), almost 2 miles in length, was completed
in 1997. The second part, 4.5 miles from NC 68 to US
29/70 (Business Loop I-85), was opened on November 20,
2004 after a delay of nearly a year (2). Once this section
was completed, US 311 was re-routed along the completed
bypass to Business 85 then south to its old route. The exits on both parts were
first numbered based on US 311 mileposts, but were renumbered
in 2008 to I-74 based mileposts (for an I-74 exit list, go
HERE), to match
those put up at the same time on Segment 5. The newly opened section,
like its older predecessor, appears to
be up to interstate standards, however NCDOT
has indicated that some parts are or will not be built
to these standards initially. (3) Though some news reports
have indicated NCDOT is not planning to sign the highway
as I-74 until the freeway is completed to US 220 (I-73), (2) documents posted by NCDOT for the last section contract
letting in late 2006 included detailed plans showing the placement
of I-74 signage along the entire stretch of highway at the conclusion
of the project. (4) Photos from the two complete sections are
below and at the bottom of the page. The Right-of Way acquisition
phase for the last part (6.7 miles from Business 85 across
I-85 to Tuttle Road, SR 1920 near Archdale) was delayed
a year, to 2003, due to environmental concerns about
the road's path being near the new Randleman Reservoir,
a future drinking water source for Greensboro. (5,6) For the 2007 contract letting
this segment was split further into smaller pieces with part of the
contract (a one mile piece east of I-85 to Tuttle Road) assigned to
the contract for the next segment (R-2606). The winning contractor, Blythe
Construction put in a combined bid ($104 million) for both projects.
Construction started on May 31, 2007 three years after first scheduled
for 2004. (7) There was a ceremonial groundbreaking for the project on
July 16, 2007, for the official press release go HERE.
(8) According to the NCDOT press release indicating
the contract was approved, the tentative completion
date was May 2011 (the press release indicated the mileage
for the entire project from Business 85 to Spencer Road was
6.4 miles, this was due to an error in the letting documents
that indicated the distance was in kilometers, someone at NCDOT
dutifully translated the given distance of 10.2 'km' back
to miles). (9) New calculations put the distance at
over 7 miles. However, NCDOT announced in March 2010 that the road
could be open by that November. (10) As indicated in the 2009-2015
STIP, total costs for building this entire segment are
now estimated at $242.8 million. (1) The I-85 interchange will
be near the existing NC 62 exit, traffic will exit for both NC 62
(to be Exit 113A) and I-74/US 311 (Exits 113B and C) using the same
exit ramp on I-85 south. (4) In May 2008 in anticipation of construction
of the I-85 interchange they closed the ramp from NC 62 to I-85 South
and have started putting fill in the area surrounding the interchange.
I-74 will pass under I-85 so it will was necessary to build the C/D
ramps for the future I-74 interchange first and then, in October 2008,
place I-85 in both directions temporarily on these ramps so that bridges
can be constructed for I-85 to go over I-74 without affecting traffic.
(11) The new bridges appeared close to completion in March 2010 and
NCDOT was in the process of putting up overhead signs in the area in advance
of re-opening the I-85 lanes during April and May. As of the end of June
this segment and the next combined were 91.1% complete. (7)
Photos taken along the completed parts of the US 311 Bypass parts in 2004 (Segments 1 and 2):
Photo shows Kivett Drive ramp being constructed a year before it opened to US 311 South. (October 2003)
The US 311 Bypass (I-74) interchange and bridge over Kivett Drive in High Point almost a year later, the day after the bypass opened. (November 21, 2004)
Here' the unopened ramp from I-74 West/ US 311 North which leads to the current construction area (September 2007).
Here is a summary of the progress of current construction (now 92% complete) on the remaining section through July 2010 going west to east, with photos (from most recent to oldest) below. All the major (over roads) and minor bridges (over streams) are now complete. (12):
Baker Rd.
Bridge - The new bridge was completed in early February
2010 after an 8 month project that started in June 2009. Traffic
was put onto a temporary road to the north, completed in June therefore
not requiring a detour until the new bridge was completed. Work started
on the bridge in July 2009 and by the middle of January 2010 it appeared
almost ready to open. Concrete for the roadbed had been completed and
asphalt was being laid to connect the bridge to the old road alignment
as seen in the photo below. The bridge was not opened to traffic though
until early March, a delay probably due to weather problems preventing
lane markings from being put down:
View driving over the newly opened bridge, heading
west, in March 2010. (3/10/10)
View of the open bridge looking eastbound a month
earlier, the removal of the temporary road had yet not begun due to
the need to remove rock in the freeway's path first. (3/10/10)
The bridge appears complete,
except for lane markings in this view taken in late January. (1/28/09)
Workers laying asphalt at west end of new
Baker Road Bridge. (1/14/10)
The
crane can be seen lowering the first beam into place in early
October. (10/12/09)
A closer
look at the equipment that loads the support sections in place,
three sections make up one span for the bridge. (10/12/09).
Looking east in September when the
crane had just been brought in to lift the concrete forms into
place and then the bridge girders in October. (9/18/09)
Jackson Lake
Road Bridge - This bridge was completed and opened to traffic
at the end of November 2008.
This photo is after the roadway around the bridge received
its final coat of asphalt in April 2010. (5/9/10)
Here's a view of the
bridge soon after it opened heading south across it toward NC
610. The changes since have mainly consisted of consolidating
the excavated material besides the road bed, so it can be removed,
this was still going on in early August 2009. (11/23/08)
The view east from the bridge in November 2008, notice progress on excavation, but where the roadway will be is not as obvious as it is a year later. (11/23/08)
Kersey Valley
Rd. - This bridge was completed in October 2008.
The view
of the bridge in December is very much like that of a month earlier,
notice the addition of asphalt on the future roadway, as compared
to the view in September, below. (12/12/09)
The view of the bridge from Dresden
Road in September 2009, notice less piles of dirt and more construction
vehicles and equipment than in the photos below. This is because much
of the dirt has been pushed off and up from the road bed.
(9/18/09)
The
excavated materials have been piled on the side of the eastbound
lanes during the summer of 2009. What's left in the roadbed median
are construction materials that were there in the July as seen in
the photo below. (9/18/09)
Here's the view from late October showing what was excavated at that time, including the roadway later removed (see above) (which already had been blocked by barriers) in the center. (10/31/08)
Similar view as above showing progress of clearing and grading the future I-74 roadway between I-85 and Kersey Valley Road in November 2009. Compare with the view above and below from last spring. (11/8/09)
The appearance of the future I-74 roadway between I-85 and Kersey Valley Road from April 2009. (4/5/09)
Here's the view in October 2008, showing the beginnings of grading of the roadway. (10/31/08)
The I-85 / US 311 - I-74
interchange.
Footings for bridge structures were completed
over the summer of 2008 and C/D lanes constructed for the future
interchange, traffic was switched on I-85 in both directions
onto the C/D lanes once completed in October 2008 so the I-85
road could be excavated for the I-74 freeway. Significant progress
has since been made on on both the I-85 bridges and building the flyover
ramp that will carry I-74 East traffic to I-85 north. The original
I-85 roadway reopened in mid-April 2010. Compare the photo below to those
taken in July 2010 and those in early April 2009 and in November 2008.
Work
still remains on building the walls for the I-85 roadway over
I-74, there also appears to be little asphalt on the southern roadbed
after the flyover. (11/8/09)
This is the bridge over I-85
going north, unfortunately, they put back up the fence surrounding
the highway, so I could not duplicate the shots from below, but
had to take two. (6/14/09)
This is a complete photo of the I-85 South future interchange with I-74 in April 2009. The future I-74 and NC 62 exit C/D lanes were now serving as the I-85 mainline temporarily as the old road is excavated (the start of which is going on behind the bridge) to put I-74/US 311 under existing I-85. Above is the progress of construction as of April.
The same view from late October 2008. (10/31/08).
The view of the now cut-off Dresden Road in April 2009 with the future I-85/I-74 interchange in the distance. (5/5/09)
A similar view from April shows progress on the I-85 bridges at that time and the beginnings of the construction of the ramp from I-74 east to I-85 and its continuance on the flyover ramp in the distance. (4/5/09)
Here is a similar photo from fall 2008. The bridge above I-85 is a part of the I-74 east interchange fly-over ramp, you can see that the ramp to I-85 south is already paved. (11/23/08)
You can also see in this photo that the closed southbound lanes of I-85 has been excavated by November 2008. (11/23/08)
Better
photo of new exit sign, from I-85, showing NC 62 Exit now designated
113A. (5/9/10)
Photo from July 2010 showing sign assemblies, and signs had been
put up, the future exit signs covered over. (7/25/10)
As mentioned above this ramp system southbound will also serve as access to NC 62. These ramps were closed for much of October as they were re-aligned to meet the new C/D ramps. The exit number will be changed to 113A. (10/31/08)
Exit 65 US 311 Business* High Point [25]
Exit 66 Johnston
St [24]
Exit 67 NC
68 to I-40 Eastchester Drive [23]
Exit 69 Greensboro
Rd [21]
Exit 70 Kivett
Drive [20]
Exit 71A Green Street
(WB only) [19B]
Exit 71 (71B
WB) Bus. Loop 85/ US 27/ US 70 Thomasville Greensboro
[19(A)]
This will be applied
when the freeway is completed in 2011:
Exit 75A/B
I-85 Greensboro Charlotte
Here are some photos of
the US 311 signs with the new numbers:
Going Eastbound (north of
US 311), this is the first overhead with two exit signs showing
the new numbers. (12/14/08)
Continuing East you have signs for the Greensboro Road and NC 68 exits. (12/14/08)
The route goes to two lanes westbound after the Exit 67 exit. (12/14/08)
As you can see, they're not ready to put up I-74 signs on the BGSs or along the highway at this time. (12/14/08)
Here's the current end of the US 311 freeway at
Business 85, the next exit will be at I-85, Exit
75. (12/14/08)
If anyone has other photos taken in the vicinity of this segment they would like to share, feel free to E-mail me.
Sources: Map-ADC North Carolina Road Atlas 1999, p. 124;
(1) NCDOT. June 2008. State Transportation
Improvement Program, 2009-2015, Division 7, p.7-18.
(2) Dominello, Amy. 20 http://www.digtriad.com/news/local/article.aspx?storyid=139506&catid=57,
March 29.
(11) Information via e-mail from
Bill Travers 5/23/08.
(12) Information
from e-mails from Bill Travers 8/11/08, 10/20/08, 6/13/09,
8/2/09, 3/. 05. "U.S. 311 Bypass Work
Delayed." News
& Record (Greensboro, NC). May 2, downloaded
from http://blog.news-record.com/staff/fastforward/archives/2005/05/from_sundays_pa.html,
Oct. 1.
(3) NCDOT. 2006.
"I-73/74 Fact Sheet, Interstate System 50th Anniversary."
Downloaded from lhttp://www.ncdot.org/ public/50thanniv/ncinterstates/download/factsI73-74.pdf
(4) NCDOT. 2006.
Contract Documents, NCDOT Signing Section, Contract
C201275, Project R-0609-IA. Downloaded from link at: http://dotw-xfer01.dot.
state.nc.us/dsplan/2007%20Highway%20Lettings/4-17-2007/
on 2/17/07.
(5) Schultz,
Sue and Paul Muschick. 2002. "State Puts Conditions
on Bypass; Officials Are Struggling to Build
a Highway Near the Randleman Reservoir." News-
Record (Greensboro, NC), High
Point/Randolph/Rockingham Edition. Feb. 14: B1.
(6) Johnson, Paul B. 2004. "Bypass Opening Stalls."
High Point Enterprise. Sept. 22.
(7) NCDOT.
2010. Construction Progress Report, Contract C201715,
last downloaded June 7, 2010.
(8) Journal Staff. 2007.
"REGIONAL BRIEFS-Ground to be Broken for Next
Leg of Corridor." Winston-Salem Journal. July 10.
(9) NCDOT. 2007.
"Transportation Board Awards $104.2 Million Contract
to Construct 6.4 Miles of U.S. 311 in Guilford and Randolph
Counties." Press Release. May 4. Downloaded from https://apps.dot.state.nc.us/pio/releases/details.aspx?r=1135,
May 4, 2007.
(10) Lanse, Sarah. "Highway. 311 Bypass To Open By End of
Year." WMFY-TV 2 . March 4.
(11) Various E-mails from Bill Travers, last dated 3/24/10.
I-74 and US 311 shields courtesy of David R. Kendrick's Shield's Up!
|
|
|