Segment 7
|
Where:
South of I-85 near Archdale to US 220, near Sophia,
Randolph County
Length: 13 Miles Needed: Finish Constructing New Freeway Current Highway signed:
|
I-74 will continue on a new freeway
from south of I-85 near current Exit 113 in Archdale to US 220 (I-73)
near Sophia, north of Asheboro, connecting to US 220 south of the current
US 311 interchange along a path approximated by the
red dashed line in the map above. When this specific route
was chosen in 1997 it disappointed many citizens and government
officials in the area since the route cuts a 1000 foot wide path
directly through the city of Sophia before meeting US 220. Despite
many objections, NCDOT chose this route, designated Corridor C,
rather than the Corridor AA route prefered by the public at June
1997 hearings, because it cost $7 million less, avoided a complicated
interchange with US 220 (I-73), and would send the least amount of
pollution to the future Randleman Reservoir, preventing potential
environmental problems. (1, 2) The project is listed in the 2009-2015
NCDOT STIP as Number R-2606. (3) Right-of-Way acquisition started
on the western part of the route in 2003, with a total cost projected
at $17.5 million. Construction on the first section, $28.5
million of the total construction cost estimated
at $177 million, started on May 29, 2007 (see below). (4) This section
will feature an interchange at Cedar Square Road (listed in contract
documents as Exit 79) which will be the temporary end of I-74 while
the other segments are still under construction. US 311 will be
temporarily routed along Cedar Square road back to its current
alignment. The US 311 route from there westward (northward) will
be redesignated US 311 Business. (5) The next two segments totalling
7.9 miles will be built as design-build projects. These were let in August
2008 with Barnhill Contracting being the winning bidder with a cost
of $99.7 million. Construction started in September 2008 and is now listed
as 7% complete. (4) There will be an additional exit where the freeway
crosses the current US 311 in Sophia and the interchange with US 220
at the end of this segment. (6)
This
segment has been dubbed the "Missing Link" by the
I-74 Piedmont Corridor Group (PCG), an organization of
business people, transportation officials, and others
lobbying to complete I-74. They created the term in 2003 to
call attention to what they saw as NCDOT's too drawn-out segmented
plan to complete this portion of the highway, long after many
other sections of I-74 were then scheduled to be built. The
PGC hoped to put enough pressure on NCDOT to move up its construction
timetable for the entire section to match work starting on Segment 6 to the west. Starting
both projects at once, supporters said, would be more efficient.
(7) This effort seems to have eventually paid
off. While start of construction was delayed from
October 2006 to May 2007, work on the first part, 5.3 miles
from south of I-85 near Archdale to north of Spencer Road (SR
1929) in Glenola,(8) will began at the same time as work was started
on the remaining section of Segment 6. (9)
Also, whereas earlier plans called for the proposed
letting for the next part of the highway, 5.6 miles from
Spencer Road to the current US 311 west of Sophia, not to occur
until after 2012 and the final part, 2.3 miles from current
US 311 to US 220 through Sophia not to begin a couple years
after that (10), the new STIP indicates most of the funds
will be borrowed under the Garvee Bond Program to expedite work
on the next two sections starting in the latter half of 2008. These
borrowed funds ($112 million) would then be paid back out of the
highway fund accounts through 2019. (3) The first section then
should be completed by May 2011, or earlier, and the entire segment
may be finished by Fall 2012.
A
summary of construction on the first section from west to east, with photos
below, through mid-November 2009 (11):
The I-85/I-74
Interchange Flyover Ramp:
The ramp as it appeared
in November 2009, note still the need to put in concrete walls along the
bridge structure, the container units are on the future on-ramp to I-74 East.
(11/8/09)
In mid-June the
decking needed more attention, the future ramps and I-74 roadway had
received at least one coat of asphalt around the I-85 interchange (6/14/09).
A view from 2 months earlier, showing the progress on constructing the flyover ramp from I-74 East, the bridge decking was in place awaiting cement pouring. (4/5/09)
Here's another
view of what was in place on the bridge pier in April, part of the flyover
ramp from I-74 East. (4/5/09)
View of the same bridge structure about five months earlier, not much progress here, though the bridge piers in the background have been constructed and are near completion. (11/23/08)
A completed bridge pier can be seen in the distance, from the now split Checker Road, now, since disconnected, renamed Modlin Grove Road, due to I-74 construction as of early 2008. (2/23/08)
Road grading was just starting east of I-85 and west of NC 62 back in Feb. 2008. Taken just after the split of then Checker Road. (2/23/08)
Looking eastbound at the clearing being done for the interchange from I-85 North, September 2007.
Here's the view approaching the construction area on I-85 North, lanes were restricted in the area from 3 to 2, for I-74 construction a month earlier (September 2007).
Here's a view to the opposite side of the bridge showing the progress of land clearing a couple miles east of NC 62 in the Fall of 2007. (September 2007)
Tuttle Road Bridge - This
was the first bridge completed in this segment. Started in the spring
of 2007, graded fill was placed up to the western edge of where the
completed bridge in May 2008. The bridge was open early in August
2008. The following are photos from June 2009.
The end of the US 311 construction zone, The next traffic light is for Spencer Road, the end point for the first part of the project. (9/18/09)
The end of the first phase of the project just north of Spencer Road in September 2009. (9/18/09)
More signs of work could
be seen in November 2009 for the next segment to be constructed
from Spencer Road to US 220 along US 311. But there were some signs work
was starting:
Comment: After this section
of freeway is built to replace US 311, decommission
this intrastate US route which doesn't meet current AASHTO
U.S. Route guidelines (at least 200 miles long, in more than
1 state). The section north of I-40 (not along I-74's route)
could be NC 311.
Here's a map from the Greensboro
News & Record showing the new sections of I-74 under
construction:
Sources: NC Transportation Map 2001.
(1) Hall, Tony.
1997. "I-74 Coming to a Town Where It's Not Welcome."
News & Record (Greensboro, NC). Sept. 27:
B1.
(2) Muschick, Paul. 1999. "Route
for 311 Bypass to be Unveiled in Randleman." News
& Record (Greensboro, NC). August 9.
(3) NCDOT. June
2008. State Transportation Improvement Program, 2009-2015,
Division 8, p. 8-27.
(4) NCDOT. 2007. Construction Progress
Report, Contract C201715, Downloaded June 15, 2009.
(5) NCDOT. 2006.
Contract Documents, NCDOT Signing Section, Contract C201296,
Project R-0609-A. Downloaded from link at: http://dotw-xfer01.dot.
state.nc.us/dsplan/2007%20Highway%20Lettings/4-17-2007/ on 2/23/07.
(6) NCDOT. 2008. "Transportation Board
Awards More than $265 Million in Highway Contracts for 29 Counties."
Press Release. NCDOT Communications Division, 8/7/08.
(7) Kimbrough,
Pat. 2003. "Randolph Leaders Lobby State for I-74."
High Point (NC) Enterprise. Dec. 1.
(8) NCDOT. 2007. Program Development
Branch. "12 Month Tentative Letting List for April
17, 2007" (Typically construction projects are approved
and/or start a month after the project is let, this project
is to start the last week in May).
(9) Dominello, Amy. 2005.
"U.S. 311 Bypass Work Delayed."
News & Record (Greensboro, NC). May 2, downloaded
from http://blog.news-record.com/staff/fastforward/archives/2005/05/from_sundays_pa.html,
Oct. 1.
(10) NCDOT. Sept. 2004. R-2606 Project Breakdown
Map.
(11) Information from e-mails
from Bill Travers 3/6/08, 5/23/08, 8/11/08, 10/20/08, 2/7/09, 8/5/09.
(12) Information from e-mail from Ronald Shaw 3/6/09.
(13) AASHTO. 2009. Applications to Standing Committee on Highways,
Special Committee on U.S. Route Numbering, October 1. NC Petition Regarding
US 311 Business in Guilford County. Downloaded from: http://cms.transportation.org/sites/route/docs/NC%20Elim%20US%20311%20Bus%20Guilford%20Aug%
2009.pdf 10/2/09.
US 311 shield courtesy of David R. Kendrick's Shield's
Up!
|
|
|